Willinga Park

Over the last 10 years Shepherd has had a constant presence at Willinga Park not only in the physical delivery of new Projects but also assisting in the Design, Commissioning and continual maintenance of the site.

  • Client
    Willinga Park
  • Timescale
    10 Years
  • Location
    Bawley Point, NSW
  • Industry
    Commercial
  • Service
    Communications, Critical Power, High Voltage, Lighting Control, Low Voltage
  • Pillars
    Design, Build, Commission & Maintain

WORLD CLASS

The park is a multi venue fully equipped equestrian complex comprising of a covered arena, show jumping arena, dressage arenas, campdraft arena, polocrosse field, conference centre, commercially equipped restaurant, float parking/camping and stabling for competitors and horses, pavilion-style accommodation for spectators and guests, Gymnasiums and rehabilitation facilities for both horses and riders as well as administration buildings that support the running of the complex. The icing on the cake has been the recent completion of a state of the art Veterinary hospital and ICF facility.

1.3

MW of PV

2400

kwh of Tesla Battery Storage

3

HV Generators

2300

Acres

Grid Supply

From the initial concept of this project it was apparent were going to be challenged with a Grid power supply connection that would be large enough to support of site load, With and Estimated maximum demand of approximately 4MVA during events we soon learnt that this was twice the normal load of the townships of Bawley point and Kiola added together which only surge during peak holiday events at Christmas and Easter to around 3.5MVA.

Supply Enhancement

Shepherd engaged with Endeavour energy to design and install an upgraded existing 11KV feeder to Willinga park, Bawley point and Kiola as well as install a second redundant path feeder to help with increased capacity of supply as well as provide a ring feed option should maintenance or outages be encountered.

Hybrid Power Systems

  • 1.3MW of PV
  • 2,400kwh of Tesla battery storage
  • 3 x generators at 4.3MVA prime rated
  • 70,000lt containerised diesel tank, bulk oil storage, complete fuel and oil control systems, ComAp supervisory control system
  • Centralised power house with step up transformers to 960volts to allow for long distance distribution with some submain runs exceeding 2000m
  • Auto tap changing step down transformers at remote locations to reduce the 960v distribution to local 433/240v