WORLD CLASS
The park is a multi venue fully equipped equestrian complex comprising of a covered arena, show jumping arena, dressage arenas, campdraft arena, polocrosse field, conference centre, commercially equipped restaurant, float parking/camping and stabling for competitors and horses, pavilion-style accommodation for spectators and guests, Gymnasiums and rehabilitation facilities for both horses and riders as well as administration buildings that support the running of the complex. The icing on the cake has been the recent completion of a state of the art Veterinary hospital and ICF facility.
MW of PV
kwh of Tesla Battery Storage
HV Generators
Acres
The facility continually grew to install new areas and amenities to ensure WP could host a full variety of equine events.
Grid Supply
From the initial concept of this project it was apparent were going to be challenged with a Grid power supply connection that would be large enough to support of site load, With and Estimated maximum demand of approximately 4MVA during events we soon learnt that this was twice the normal load of the townships of Bawley point and Kiola added together which only surge during peak holiday events at Christmas and Easter to around 3.5MVA.
Supply Enhancement
Shepherd engaged with Endeavour energy to design and install an upgraded existing 11KV feeder to Willinga park, Bawley point and Kiola as well as install a second redundant path feeder to help with increased capacity of supply as well as provide a ring feed option should maintenance or outages be encountered.
Hybrid Power Systems
- 1.3MW of PV
- 2,400kwh of Tesla battery storage
- 3 x generators at 4.3MVA prime rated
- 70,000lt containerised diesel tank, bulk oil storage, complete fuel and oil control systems, ComAp supervisory control system
- Centralised power house with step up transformers to 960volts to allow for long distance distribution with some submain runs exceeding 2000m
- Auto tap changing step down transformers at remote locations to reduce the 960v distribution to local 433/240v
Willinga Park carefully blended lighting to form and highlight architectural features whilst also maintaining competition level performance. All lighting control was commissioned by our in house team at Shepherd.